Project details
Project description
In July 2025, Approximately 7.3 km of 80-inch Carbon Steel pipeline welding works were completed along with insulation of around 5 km of welding joints. Additional activities included inspections, excavation, screening, and other supporting works, as part of the Ras Al-Rais Pipeline Project – Rabigh / RRJV.